1. Check before each use of the concrete mixing plant

 

Check whether the self-protection device of the air compressor in the concrete mixing plant is reliable and whether the air pressure is stable; check whether the water pump is filled enough and whether the pipeline is unobstructed; Flexible and reliable; check whether the connecting bolts of the blades of the mixing main engine are firm; check whether the electrical devices are reliable, and whether the action switches of each limit switch are flexible and reliable; check whether there is enough lubricating oil in the rapid reduction box of each lubrication point.

 

2. Maintenance after each shift

 

Clean up the inside and outside of the concrete mixer, and the accumulated material on the material door, and rinse it; fill the lubrication points at each lubrication point, especially the shaft end seal, and must not be missed; the liquid in the waterway should be drained in winter; the air compressor should be drained. Gas and accumulated water in the gas cylinder; all switches are in non-working state after shutdown, and the power supply is cut off.

 

3. Weekly inspection and maintenance

 

Check the condensation of the residual concrete in the mixing tank. If there is condensation, stop the machine and remove it (note that the power supply should be cut off and specially assigned to take care of it), check the gap between the mixing blade and the liner, and adjust it if it is not suitable; check whether the air system leaks and the cylinder operates Whether it is reliable; check the quality and liquid level of the lubricating oil in the reduction box, and fill or replace it if necessary; check whether the suction bottom valve in the water supply system is reliable; check whether the electrical components are damaged, repair or replace if necessary, check Whether the wiring is loose; unscrew it to release the silt, check the seal of the shaft end, and screw it in to release the silt if there is no abnormality.

 

4. Check and maintain all around

 

Check the tension of the belt of the concrete mixing plant and make appropriate adjustments; check the wear of the blades and liners; check whether the connecting bolts of the upper and lower racks, silos, and large inclined belt conveyors are firm and whether the foundation is down Shen; check whether there are lumps and sundries in the concrete mixing plant equipment-screw conveyor, and remove them if any.

 

5. Check, maintain and overhaul the concrete mixing plant every year

 

Concrete mixing plant equipment has been in operation for one year. In addition to inspections of items 1, 2, 3, and 4, other components should also be inspected, and all aspects should be inspected, repaired and replaced.

 