1 Concrete mixer operators must hold a certificate to work, and it is forbidden to hand over the machine to unlicensed personnel. When operating, they should concentrate on operating correctly, and must not leave the post without authorization.
2 Check the fixation, clutch, brake, pulley, wire rope, transmission device, upper hopper limit, electrical circuit, protection zero or grounding wire of the mixer before operation, and if there is any abnormality, it must be eliminated
3 When multi-shift operations are implemented, the shift system should be implemented. The successor should carefully fill in the shift record. The successor can only work after checking and confirming that the hoist is correct and signing.
4 It must be used reasonably according to the specified technical performance mechanical
5 After the upper hopper is raised, no one is allowed to enter under the hopper. When cleaning the bottom of the hopper, the safety chain must be hung. When someone in the mixing tank enters the cleaning and maintenance work, pull down the isolating switch in the switch box and lock the switch box. , so as not to hurt people by misoperation.
6 After the operation is completed, the machine should be cleaned up, the power supply should be cut off, and the switch box should be locked. I believe that after the above introduction, everyone has a certain understanding of the safety technology disclosure of the construction concrete mixer. Welcome to log in and inquire more Multiple related information.