Construction process of mixing and pumping integrated machine
1. Stir in the mixing tank
The forklift puts the sand and gravel into the hopper, and after manually pouring the cement into the upper hopper,
Then, the upper hopper runs the mixing drum, and the drum rotates to mix the concrete.
This is the first and most important stirring process.
2. Concrete in the hopper
During the process of being sucked into the conveying cylinder, the concrete is stirred twice by the mixing blades in the discharge hopper.
The discharge hopper is designed in an inclined arc shape, and two mixing blades are installed at the upper end. After the concrete is mixed in the mixing drum, the concrete is introduced into the discharge hopper.
3. Concrete is mixed in the pipeline
The third mixing of the mixing pump is realized by mixing in the pipeline, which is completed in the process from the concrete conveying pipeline to the pouring point.
In the pipeline, the spiral rotation is performed, and the corresponding stirring is also obtained in the process of rotation.
Hot Tags: 30m³/hr concrete mixer machine with pump, China 30m³/hr concrete mixer machine with pump suppliers, manufacturers, volumetric concrete mixer with pump, concrete mixer water pump, , Small Concrete Mixer Pump, concrete mixer pump capacity